ACT AppealIndia - ASIN81Kashmir Earthquake RehabilitationGeneva,
5 February 2008
Appeal
Target: US$ 389,345 On
October 8th 2005, an earthquake rocked Pakistan and North
India killing close to 100,000 people in Pakistan and about 1,500
in India. The epi-centre of the quake was in west Muzaffarabad in
Pakistan administered Kashmir. This is a follow-on appeal from ACT
Appeal ASIN61 for Indian Kashmir (rehabilitation and reconstruction
phase) which closed at the end of August 2007. The appeal is requested
by ACT member CASA (Churches Auxiliary for Social Action), India and
will be implemented directly by CASA. CASA’s proposed response
is to continue rehabilitation assistance in Pawadian village in Uri,
Kashmir through the provision of permanent shelter for 38 targeted families
and to enhance the capacities of 8 widows in the same village through
livelihood support activities. In November 2006 the Indian Government
allotted to CASA the village of Pawadian in Uri, Kashmir, just 14
km from Sokar Village in which CASA was carrying out rehabilitation
activities under ASIN61. Due to generous in-kind contributions from
private individuals, savings were made in the reconstruction of housing
in Sokar enabling CASA to budget for further housing for 29 of the
most needy families out of the 113 families in Pawadian village, almost
all of whom had suffered loss/damage to property. In addition, CASA
is proposing to take up reconstruction of an additional eight houses
in Pawadian. This
appeal was preceded by the original ACT Appeal ASSA51 for both Pakistani
and Indian Kashmir (relief and early recovery phase), and ACT Appeal
ASIN61 for Indian Kashmir (rehabilitation and reconstruction phase)
which closed at the end of August 2007. The ACT Coordinating Office
is in the process of requesting various donors approval for transfers
to this appeal of the balance of funds (US$ 389,343) for CASA under
ASIN61. Approved transfers will then be shown as income to this appeal,
as per normal ACT procedures. The appeal will close on 31 July 2008. Project
Completion Date: 31
July 2008 (commenced in October 2007, prior to the issue of this appeal) Reporting
schedule: Interim
narrative & financial:
N/A Final
narrative & financial: 30 September 2008 Audit:
31 October 2008 Signed
by: John Nduna
|
||||||||||||||||